Two tames need 18 days to complete an engineering taks.Tame A have worked 3 days.Tame B have worked 4days.They have finished one fifth of the task.If team A complete the task by them selves they need ( )days.
Two tames need 18 days to complete an engineering taks.Tame
答案:2 悬赏:30 手机版
解决时间 2021-12-28 15:35
- 提问者网友:献世佛
- 2021-12-27 19:05
最佳答案
- 五星知识达人网友:荒野風
- 2021-12-27 20:27
答案:36 (days).
假设:总任务量为1,team A的工作速度为a/天,team B的工作速度为b/天,则据题意就有:
18×(a+b)=1
3a+4b=1/5
求解上述方程得到:a=1/45;b=1/30.
当team A独自完成剩余4/5任务时,据题意就有:4/5÷1/45=36 (days).